MISO-J4046
100 MW generation in Attala, MS · In queue since July 2025
100 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
Total Duration
10 months
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4046 is a proposed 100 MW solar generation project located in Attala County, Mississippi. The project is in the MISO interconnection queue, having entered the queue on July 17, 2025. The designated point of interconnection (POI) is CONEHOMA CREEK - CARTHAGE (MS) 115.0kV. The developer is unknown.
The project's service type is NRIS (Network Resource Interconnection Service). It is currently in Phase 1 of the study phase process within the MISO queue. The proposed project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
MS
County
Attala
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
NRIS
Point of Interconnection
CONEHOMA CREEK - CARTHAGE (MS) 115.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4046