MISO-J4047
160 MW generation in Tuscola, MI · In queue since August 2025
160 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
Total Duration
9 months
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4047 is a proposed 160 MW solar generation project located in Tuscola County, Michigan. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, with a queue entry date of August 13, 2025. The designated utility for the project is METC, and the point of interconnection (POI) is the KARN - THETFORD (ATLANTA) 138.0kV substation. The project's service type is NRIS (Network Resource Interconnection Service).
The development project is currently listed as active in the MISO queue.
Generated from interconnection queue and public data sources
State
MI
County
Tuscola
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
KARN - THETFORD (ATLANTA) 138.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.