MISO-J4049
75 MW generation in Ouachita, LA · In queue since August 2025
75 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
Total Duration
9 months
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4049 is a proposed 75 MW solar generation project located in Ouachita County, Louisiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue with an entry date of August 28, 2025. The project's service type is Network Resource Interconnection Service (NRIS) and it is currently in Phase 1 of the study phase.
The project is listed as "active" in the MISO queue. The point of interconnection (POI) is RILLA.
Generated from interconnection queue and public data sources
State
LA
County
Ouachita
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
NRIS
Point of Interconnection
RILLA
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4049