MISO-J4053
200 MW storage in Grand Traverse, MI · In queue since July 2025
200 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
Total Duration
10 months
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4053 is a proposed 200 MW battery storage project located in Grand Traverse County, Michigan. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of July 28, 2025. The designated point of interconnection (POI) is the KEYSTONE - WEXFORD 138.0kV substation. The project's service type is listed as NRIS (Network Resource Interconnection Service).
The project's developer is unknown, but the interconnecting utility is Michigan Electric Transmission Company (METC). As of the latest data, the project has an active status in the MISO queue, but a proposed commercial operation date and interconnection agreement (IA) status are not available. There is no indication that this project is linked to an existing operating plant or has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
MI
County
Grand Traverse
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
KEYSTONE - WEXFORD 138.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4053