MISO-J4054
146 MW generation in Saginaw, MI · In queue since September 2025
146 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
Total Duration
8 months
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4054 is a proposed wind generation project located in Saginaw County, Michigan, within the Midcontinent Independent System Operator (MISO) region. The project, with a total capacity of 146 MW, is listed in the MISO interconnection queue as of September 18, 2025. The designated point of interconnection (POI) is the CLAREMONT - LAYTON 138.0kV substation.
The project's service type is designated as NRIS (Network Resource Interconnection Service). The queue status is currently active. The developer is unknown, but the interconnecting utility is listed as METC.
Generated from interconnection queue and public data sources
State
MI
County
Saginaw
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
CLAREMONT - LAYTON 138.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.