MISO-J4055
198 MW generation in Ionia, MI · In queue since August 2025
198 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
Total Duration
9 months
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4055 is a proposed 198 MW wind generation project located in Ionia County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on August 29, 2025. The designated point of interconnection (POI) is Peddler, and the requested service type is NRIS-Only.
The transmission utility for the project is ITC. As of the latest data, the project remains in active status within the MISO queue.
Generated from interconnection queue and public data sources
State
MI
County
Ionia
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC
Entity
MISO
Service Type
NRIS-Only
Point of Interconnection
Peddler
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4055