MISO-J4057
127.4 MW generation in Mower, MN · In queue since August 2025
127.4 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
Total Duration
9 months
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4057 is a proposed solar generation project with a total capacity of 127.4 MW. The project is located in Mower County, Minnesota, and is in the MISO interconnection queue. The queue entry date is August 22, 2025. The project's point of interconnection is the YANKEE substation. It is currently in Phase 1 of the study phase.
The project is seeking Non-Retail Interconnection Service (NRIS) from MISO. As of the latest data, the project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
MN
County
Mower
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
NRIS
Point of Interconnection
YANKEE
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Yankee Doodle Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.