MISO-J4059
129 MW generation in McLeod, MN · In queue since August 2025
129 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
Total Duration
9 months
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4059 is a proposed 129 MW solar generation project located in McLeod County, Minnesota. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of August 20, 2025. Northern States Power Company is the interconnecting utility.
The project's interconnection service type is Network Resource Interconnection Service (NRIS). As of the latest data, the project is in Phase 1 of the MISO interconnection study process. The point of interconnection (POI) is the Blue Lake - MCLEOD (GRE) 230.0kV substation.
Generated from interconnection queue and public data sources
State
MN
County
McLeod
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Blue Lake - MCLEOD (GRE) 230.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4059