MISO-J4065
200 MW storage in Dakota, MN · In queue since September 2025
200 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
Total Duration
8 months
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4065 is a proposed 200 MW battery storage project located in Dakota County, Minnesota. The project is being developed within the Midcontinent Independent System Operator (MISO) region and is listed in the interconnection queue under queue ID MISO-J4065. Great River Energy is the utility associated with the project.
The project entered the MISO queue on September 22, 2025. It is currently in Phase 1 of the study phase and is seeking Non-Retail Interconnection Service (NRIS). The point of interconnection (POI) is the Nininger 115 kV substation. The project's status is currently listed as active.
Generated from interconnection queue and public data sources
State
MN
County
Dakota
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
GREAT RIVER ENERGY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Nininger 115 kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.