MISO-J4073
200 MW generation in Coahoma, MS · In queue since September 2025
200 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
Total Duration
8 months
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4073 is a proposed 200 MW solar generation project located in Coahoma County, Mississippi. The project is in the MISO interconnection queue, having entered on September 29, 2025. The designated point of interconnection (POI) is the Lula - Jonestown substation at 115 kV. Entergy Mississippi, LLC. is the utility associated with the project.
The project's interconnection service type is NRIS (Network Resource Interconnection Service). As of the latest data, the project's status is active and it is in Phase 1 of the study phase.
Generated from interconnection queue and public data sources
State
MS
County
Coahoma
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
NRIS
Point of Interconnection
LULA - JONESTOWN SS 115.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4073