MISO-J4074
300 MW generation in Crittenden, AR · In queue since September 2025
300 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
Total Duration
8 months
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4074 is a proposed 300 MW solar generation project located in Crittenden County, Arkansas. The project is being developed within the Entergy Arkansas service area and has an interconnection request in the Midcontinent Independent System Operator (MISO) queue. The queue entry date is September 29, 2025. The project's interconnection service type is NRIS (Network Resource Interconnection Service), and it is currently in Phase 1 of the study phase.
The project is listed as active in the MISO interconnection queue. The point of interconnection (POI) is TWIST.
Generated from interconnection queue and public data sources
State
AR
County
Crittenden
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS, LLC
Entity
MISO
Service Type
NRIS
Point of Interconnection
TWIST
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- HIGH
- POI Substation
- Twist Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4074