MISO-J4086
120 MW generation in Wapello, IA · In queue since October 2025
120 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
Total Duration
7 months
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed MISO-J4086 project is a 120 MW solar generation project located in Wapello County, Iowa. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of October 7, 2025. The point of interconnection is the Ottumwa Generation - Tri-County 161kV substation, and the requested service type is NRIS (Network Resource Interconnection Service).
The project is currently listed as active in the interconnection queue. ITC MIDWEST is the utility associated with the interconnection. There has been recent news coverage of the project.
Generated from interconnection queue and public data sources
State
IA
County
Wapello
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ITC MIDWEST
Entity
MISO
Service Type
NRIS
Point of Interconnection
Ottumwa Generation - Tri-County 161kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ALTW.OTTUMW1
- POI Substation
- Ottumwa Generation Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4086