MISO-J4097
71.5 MW generation in Rock, WI · In queue since October 2025
71.5 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
Total Duration
7 months
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4097 is a proposed solar generation project with a total capacity of 71.5 MW, located in Rock County, Wisconsin. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue with an entry date of October 6, 2025. The point of interconnection is the New J1377 ATC Switching Station.
The project's interconnection request is for Network Resource Interconnection Service (NRIS) and is currently in Phase 1 of the study phase. The project is listed as active in the MISO queue.
Generated from interconnection queue and public data sources
State
WI
County
Rock
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
NRIS
Point of Interconnection
New J1377 ATC Switching Station
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4097