Project MISO-J4097 — Project Summary

Queue ID
MISO-J4097
Capacity
71.5 MW
Technology
Solar
Status
active
Location
Rock, WI
Region
MISO
Developer
IA Status

MISO-J4097

MISO-J4097BetaActiveSolarMISOLive · MISO

71.5 MW generation in Rock, WI · In queue since October 2025

71.5 MW

Capacity

0

Components

7 months

In Queue

IA Status

Interconnection

Total Duration

7 months

Study Phase

Phase 1

Pre-Study0%
Queue EntryOct 6, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

MISO-J4097 is a proposed solar generation project with a total capacity of 71.5 MW, located in Rock County, Wisconsin. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue with an entry date of October 6, 2025. The point of interconnection is the New J1377 ATC Switching Station.

The project's interconnection request is for Network Resource Interconnection Service (NRIS) and is currently in Phase 1 of the study phase. The project is listed as active in the MISO queue.

Generated from interconnection queue and public data sources

Project Details

State

WI

County

Rock

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

Entity

MISO

Service Type

NRIS

Point of Interconnection

New J1377 ATC Switching Station

Data Source

Live · MISO

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MINN.HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J4097