MISO-J4110
400 MW generation in Lafayette, LA · In queue since October 2025
400 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
Total Duration
7 months
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4110 is a proposed 400 MW gas-fired generation project located in Lafayette County, Louisiana. The project is being developed by CLECO POWER LLC and is listed in the Midcontinent Independent System Operator (MISO) interconnection queue. The queue entry date is October 7, 2025.
The project's point of interconnection (POI) is at the Rork - Sellers Road 230.0kV substation. The requested service type is NRIS (Network Resource Interconnection Service). The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
LA
County
Lafayette
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
CLECO POWER LLC
Entity
MISO
Service Type
NRIS
Point of Interconnection
Rork - Sellers Road 230.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.