Project MISO-J4116 — Project Summary

Queue ID
MISO-J4116
Capacity
950 MW
Technology
Gas
Status
active
Location
Walworth, WI
Region
MISO
Developer
IA Status

MISO-J4116

MISO-J4116BetaActiveGasMISOLive · MISO

950 MW generation in Walworth, WI · In queue since October 2025

950 MW

Capacity

0

Components

7 months

In Queue

IA Status

Interconnection

Total Duration

7 months

Study Phase

Phase 1

Pre-Study0%
Queue EntryOct 6, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

MISO-J4116 is a proposed 950 MW gas-fired generation project located in Walworth County, Wisconsin. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of October 6, 2025. American Transmission Company is the utility associated with the interconnection. The point of interconnection (POI) is the Sugar Creek 345 kV substation. The project's service type is Network Resource Interconnection Service (NRIS), and it is currently in Phase 1 of the study phase.

The project is listed as "active" in the MISO queue. No proposed commercial operation date or interconnection agreement (IA) status is available. No developer is listed in the queue data, and there is no match to an existing Energy Information Administration (EIA) operating plant. There is no indication of recent news coverage for this proposed project.

Generated from interconnection queue and public data sources

Project Details

State

WI

County

Walworth

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

AMERICAN TRANSMISSION COMPANY

Entity

MISO

Service Type

NRIS

Point of Interconnection

Sugar Creek 345 kV

Data Source

Live · MISO

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MINN.HUB
Hub Confidence
HIGH
POI Substation
Sugar Creek Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J4116