MISO-J4118
250 MW storage in McLean, IL · In queue since September 2025
250 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
Total Duration
8 months
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4118 is a proposed 250 MW battery storage project located in McLean County, Illinois. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue with a queue entry date of September 24, 2025. The point of interconnection is the Radbourn 345kV (LRTP-41) substation.
The project's service type is listed as NRIS (Network Resource Interconnection Service). As of the latest data, the project remains in active status within the MISO queue.
Generated from interconnection queue and public data sources
State
IL
County
McLean
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
NRIS
Point of Interconnection
Radbourn 345kV (LRTP-41)
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4118