200 MW generation in Otter Tail, MN · In queue since October 2025
200 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
Total Duration
7 months
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4129 is a proposed 200 MW wind generation project located in Otter Tail County, Minnesota. The project is being developed within the Midcontinent Independent System Operator (MISO) region and is interconnected to the Alexandria - Bison 345.0kV point of interconnection. Great River Energy is listed as the utility.
The project entered the MISO interconnection queue on October 1, 2025. It is currently in Phase 1 of the interconnection study process and has a service type of NRIS (Network Resource Interconnection Service). The project's status is listed as active.
Generated from interconnection queue and public data sources
State
MN
County
Otter Tail
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
GREAT RIVER ENERGY
Entity
MISO
Service Type
NRIS
Point of Interconnection
ALEXANDRIA - BISON 345.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Alexandria
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.