MISO-J4131
100 MW storage in Scott, MS · In queue since October 2025
100 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
Total Duration
7 months
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4131 is a proposed 100 MW battery storage project located in Scott County, Mississippi. The project is in the MISO interconnection queue, with an entry date of October 1, 2025. Entergy Mississippi, LLC. is the utility associated with the project.
The proposed project's service type is NRIS (Network Resource Interconnection Service). As of its queue entry, the project is in Phase 1 of the MISO interconnection study process. The point of interconnection is the J1347 to Switchyard (115kV Entergy MS Switchyard).
Generated from interconnection queue and public data sources
State
MS
County
Scott
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY MISSISSIPPI, LLC.
Entity
MISO
Service Type
NRIS
Point of Interconnection
J1347 TO Switchyard (115kV Entergy MS Switchyard)
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Kirk Switchyard
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4131