MISO-J4138
805 MW generation in Iberville, LA · In queue since October 2025
805 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
Total Duration
7 months
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4138 is a proposed 805 MW gas-fired generation project located in Iberville County, Louisiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue with a queue entry date of October 7, 2025. The designated point of interconnection is WEBRE, and the project is seeking Network Resource Interconnection Service (NRIS).
The project is currently listed as active within the MISO queue. No developer is specified in the queue data, and a proposed commercial operation date is not available. There is no indication of an executed Interconnection Agreement (IA) or news coverage for this project.
Generated from interconnection queue and public data sources
State
LA
County
Iberville
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
NRIS
Point of Interconnection
WEBRE
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Webre Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.