MISO-J4157
150 MW generation in Morrison, MN · In queue since October 2025
150 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
Total Duration
7 months
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4157 is a proposed 150 MW wind generation project located in Morrison County, Minnesota. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue with an entry date of October 3, 2025. Minnesota Power Inc. is the utility associated with the project.
The project's interconnection service type is Network Resource Interconnection Service (NRIS), and it is currently in Phase 1 of the study process. The point of interconnection (POI) is the Iron Ridge - Benton 345kV line. The project's status is listed as active.
Generated from interconnection queue and public data sources
State
MN
County
Morrison
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MINNESOTA POWER INC.
Entity
MISO
Service Type
NRIS
Point of Interconnection
Iron Ridge - Benton 345kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4157