MISO-J4159
664 MW generation in Ottawa, MI · In queue since August 2025
664 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
Total Duration
9 months
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4159 is a proposed 664 MW gas-fired generation project located in Ottawa County, Michigan. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of August 13, 2025. The designated utility is METC, and the point of interconnection (POI) is ROOSEVELT. The service type requested is NRIS (Network Resource Interconnection Service).
The project is currently listed as active in the MISO queue. No proposed commercial operation date or interconnection agreement (IA) status is available in the provided data. There is no indication of an EIA match to an existing operating plant, nor is there any information about recent news coverage.
Generated from interconnection queue and public data sources
State
MI
County
Ottawa
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
NRIS
Point of Interconnection
ROOSEVELT
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CONS.ZEELAND1A
- POI Substation
- Roosevelt Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.