MISO-J4170
172 MW generation in Richland, ND · In queue since October 2025
172 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
Total Duration
7 months
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4170 is a proposed 172 MW hybrid generation project located in Richland County, North Dakota. The project, which is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, entered the queue on October 7, 2025. Otter Tail Power Company is the interconnecting utility.
The project is listed as "Other" technology type, with a technology detail of "Hybrid". The proposed point of interconnection (POI) is the Hankinson - Wahpeton 230.0kV line. The requested service type is NRIS (Network Resource Interconnection Service).
Generated from interconnection queue and public data sources
State
ND
County
Richland
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
OTTER TAIL POWER COMPANY
Entity
MISO
Service Type
NRIS
Point of Interconnection
Hankinson - Wahpeton 230.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.