MISO-J4188
140 MW generation in Beauregard, LA · In queue since October 2025
140 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
Total Duration
7 months
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4188 is a proposed 140 MW solar generation project located in Beauregard County, Louisiana. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of October 3, 2025. The proposed point of interconnection (POI) is the Cole - Cooper 230.0kV line. CLECO POWER LLC is the utility associated with the project.
The project's interconnection service type is Network Resource Interconnection Service (NRIS), and it is currently in Phase 1 of the study phase. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
LA
County
Beauregard
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
CLECO POWER LLC
Entity
MISO
Service Type
NRIS
Point of Interconnection
Cole - Cooper 230.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J4188