MISO-J4198
250 MW storage in Christian, IL · In queue since September 2025
250 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
Total Duration
8 months
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4198 is a proposed 250 MW battery storage project located in Christian County, Illinois. The project, utilizing battery storage technology, is in the Midcontinent Independent System Operator (MISO) interconnection queue with a queue entry date of September 3, 2025. The point of interconnection is the Pana 138 kV substation.
The project's service type is Network Resource Interconnection Service (NRIS) and it is currently listed as active in the MISO queue. A proposed commercial operation date is not available in the queue data.
Generated from interconnection queue and public data sources
State
IL
County
Christian
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
NRIS
Point of Interconnection
Pana 138 kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- AMIL.CIPS.AZ
- POI Substation
- Pana
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.