Project MISO-J4201 — Project Summary

Queue ID
MISO-J4201
Capacity
250 MW
Technology
Other
Status
active
Location
Beauregard, LA
Region
MISO
Developer
IA Status

MISO-J4201

MISO-J4201BetaActiveHybridMISOLive · MISO

250 MW generation in Beauregard, LA · In queue since September 2025

250 MW

Capacity

0

Components

8 months

In Queue

IA Status

Interconnection

Total Duration

8 months

Study Phase

Phase 1

Pre-Study0%
Queue EntrySep 30, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

MISO-J4201 is a proposed 250 MW hybrid generation project in Beauregard County, Louisiana. The project, which is in the MISO interconnection queue, entered the queue on September 30, 2025. Cleco Power LLC is the interconnecting utility. The project's interconnection service type is NRIS, and it is currently in Phase 1 of the study phase.

The project is listed as "active" in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

LA

County

Beauregard

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

CLECO POWER LLC

Entity

MISO

Service Type

NRIS

Point of Interconnection

Cole

Data Source

Live · MISO

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
LOUISIANA.HUB
Hub Confidence
HIGH
POI Substation
Cole Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-J4201