250 MW generation in Beauregard, LA · In queue since September 2025
250 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
Total Duration
8 months
Study Phase
Phase 1
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-J4201 is a proposed 250 MW hybrid generation project in Beauregard County, Louisiana. The project, which is in the MISO interconnection queue, entered the queue on September 30, 2025. Cleco Power LLC is the interconnecting utility. The project's interconnection service type is NRIS, and it is currently in Phase 1 of the study phase.
The project is listed as "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
LA
County
Beauregard
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
CLECO POWER LLC
Entity
MISO
Service Type
NRIS
Point of Interconnection
Cole
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Cole Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.