MISO-J466
30 MW storage in MI · In queue since May 2015 · Proposed COD October 2016
30 MW
Capacity
1
Components
Battery
11 years
In Queue
IA Executed
IA Status
COD target: 2016
Total Duration
1y 5m
Schedule
117 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2016-10-01
MISO-J466 is a proposed 30 MW battery storage project located in Michigan within the Midcontinent Independent System Operator (MISO) region. The project consists of a single 30 MW battery component. Its point of interconnection is the Stein 345 kV Substation.
The project entered the MISO interconnection queue on May 18, 2015, with a proposed commercial operation date of October 1, 2016. The interconnection agreement (IA) for the project has been executed.
Generated from interconnection queue and public data sources
State
MI
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Stein 345 kV Substation
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- DECO.BROOKFLD1
- POI Substation
- Stein Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J466