MISO-J476
246 MW generation in MO · In queue since September 2015 · Proposed COD July 2020
246 MW
Capacity
1
Components
Wind
10y 8m
In Queue
IA Executed
IA Status
COD target: 2020
Total Duration
4y 10m
Schedule
71 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2020-07-01
MISO-J476 is a proposed wind generation project with a total capacity of 246 MW. The project is located in Missouri and is listed in the Midcontinent Independent System Operator (MISO) interconnection queue. The queue entry date is September 14, 2015, and the proposed commercial operation date was July 1, 2020.
The project has an Interconnection Agreement (IA) that has been executed. The point of interconnection (POI) is the Atchison County to Booneville 345 kV Line Tap.
Generated from interconnection queue and public data sources
State
MO
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Atchison County to Booneville 345 kV Line Tap
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J476