MISO-J504
50 MW generation in IA · In queue since November 2015 · Proposed COD October 2020
50 MW
Capacity
1
Components
Solar
10y 6m
In Queue
IA Executed
IA Status
COD target: 2020
Total Duration
4y 11m
Schedule
68 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2020-10-15
The proposed MISO-J504 project is a 50 MW solar generation project located in Iowa. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue with an entry date of November 13, 2015. Its proposed commercial operation date is October 15, 2020, and the project has an Interconnection Agreement (IA) executed. The point of interconnection is the 161 kV Bertram-Duane Arnold line.
Generated from interconnection queue and public data sources
State
IA
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
161 kV Bertram-Duane Arnold line
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J504