MISO-J524
100 MW generation in IA · In queue since November 2015 · Proposed COD September 2019
100 MW
Capacity
1
Components
Solar
10y 6m
In Queue
IA Executed
IA Status
COD target: 2019
Total Duration
3y 10m
Schedule
81 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2019-09-15
MISO-J524 is a proposed 100 MW solar generation project located in Iowa, interconnected within the Midcontinent Independent System Operator (MISO) region. The project, consisting of 100 MW of solar photovoltaic generation, entered the MISO interconnection queue on November 16, 2015, with a proposed commercial operation date of September 15, 2019. The interconnection agreement (IA) for the project has been executed.
The point of interconnection (POI) for MISO-J524 is the Webster substation 161 kV bus. The project's status is currently listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
IA
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Webster substation 161 kV bus
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- POI Substation
- Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J524