MISO-J569
100 MW generation in MN · In queue since May 2016 · Proposed COD April 2018
100 MW
Capacity
1
Components
Wind
10 years
In Queue
IA Executed
IA Status
COD target: 2018
Total Duration
1y 11m
Schedule
98 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2018-04-15
The proposed MISO-J569 project is a 100 MW wind generation facility located in Minnesota. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with an original queue entry date of May 6, 2016. Its proposed commercial operation date was April 15, 2018, and the project has an executed Interconnection Agreement (IA). The point of interconnection is the NSP Rock County Substation.
The development project is sponsored by MISO. Recent news coverage has discussed the project's progress and impact on the region's energy landscape.
Generated from interconnection queue and public data sources
State
MN
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
NSP Rock County Substation
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J569