MISO-J571
6.4 MW generation in MI · In queue since May 2016 · Proposed COD May 2018
6.4 MW
Capacity
1
Components
Gas
10 years
In Queue
IA Executed
IA Status
COD target: 2018
Total Duration
2 years
Schedule
96 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2018-05-31
MISO-J571 is a proposed 6.4 MW gas-fired generation project located in Kalamazoo County, Michigan. The project was entered into the Midcontinent Independent System Operator (MISO) interconnection queue on May 6, 2016, with a proposed commercial operation date of May 31, 2018. The point of interconnection is the Township of Comstock, County of Kalmazoo, Morrow 138kV.
The project's interconnection agreement (IA) has been executed.
Generated from interconnection queue and public data sources
State
MI
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Township of Comstock, County of Kalmazoo, Morrow 138kV
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.