MISO-J586
175 MW generation in AR · In queue since May 2016 · Proposed COD November 2018
175 MW
Capacity
1
Components
Solar
10 years
In Queue
IA Executed
IA Status
COD target: 2018
Total Duration
2y 6m
Schedule
91 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2018-11-01
MISO-J586 is a proposed solar generation project with a total capacity of 175 MW. The project is located in Arkansas and is interconnected within the Midcontinent Independent System Operator (MISO) region. The interconnection request was initially submitted on May 9, 2016, with a proposed commercial operation date of November 1, 2018.
The project's interconnection agreement (IA) has been executed. The point of interconnection (POI) is the EAI Crooked Lake 161kV Substation.
Generated from interconnection queue and public data sources
State
AR
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
EAI Crooked Lake 161kV Substation
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J586