MISO-J603
100 MW generation in AR · In queue since May 2016 · Proposed COD September 2018
100 MW
Capacity
1
Components
Solar
10 years
In Queue
IA Executed
IA Status
COD target: 2018
Total Duration
2y 4m
Schedule
93 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2018-09-01
MISO-J603 is a proposed 100 MW solar generation project located in Arkansas. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue with an entry date of May 9, 2016. The proposed commercial operation date is September 1, 2018, and the Interconnection Agreement (IA) has been executed.
The point of interconnection (POI) is listed as a tap on the Montrose Mist 115 kV line. The project is currently listed as active in the MISO queue.
Generated from interconnection queue and public data sources
State
AR
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Tap on Montrose – Mist 115 kV line
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- ARKANSAS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J603