MISO-J604
100 MW generation in MS · In queue since May 2016 · Proposed COD September 2018
100 MW
Capacity
1
Components
Solar
10 years
In Queue
IA Executed
IA Status
COD target: 2018
Total Duration
2y 4m
Schedule
93 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2018-09-01
The proposed MISO-J604 project is a 100 MW solar generation project located in Mississippi. The project was entered into the MISO interconnection queue on May 9, 2016, with a proposed commercial operation date of September 1, 2018. The interconnection agreement for the project has been executed.
The point of interconnection for the project is the Ruleville 115kV Substation. The project consists of 100 MW of solar photovoltaic generation.
Generated from interconnection queue and public data sources
State
MS
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Ruleville 115kV Sub
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- EMBA.SUNFLOWER
- POI Substation
- Ruleville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J604