MISO-J644
110 MW generation in IL · In queue since May 2016 · Proposed COD May 2020
110 MW
Capacity
1
Components
Solar
10 years
In Queue
IA Executed
IA Status
COD target: 2020
Total Duration
4 years
Schedule
73 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2020-05-01
The proposed MISO-J644 project is a 110 MW solar generation project located in Illinois, within the Midcontinent Independent System Operator (MISO) region. The project, consisting of 110 MW of solar photovoltaic generation, entered the MISO interconnection queue on May 9, 2016, with a proposed commercial operation date of May 1, 2020. The interconnection agreement (IA) for the project has been executed. The point of interconnection is the Jerseyville 138kV substation.
Generated from interconnection queue and public data sources
State
IL
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Point of Interconnection
Jerseyville 138kV
Data Source
LBNL
- ISO / RTO
- MISO
- Trading Hub
- ILLINOIS.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-J644