MISO-R5063
170 MW generation in Shiawassee, MI · In queue since May 2025
170 MW
Capacity
0
Components
1 year
In Queue
—
IA Status
Total Duration
1 year
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-R5063 is a proposed 170 MW hybrid generation project located in Shiawassee County, Michigan. The project, which is in the MISO interconnection queue, entered the queue on May 9, 2025. The interconnecting utility is METC.
The project's technology is listed as "Other" with a detail of "Hybrid," suggesting a combination of generation and/or storage technologies. The project is currently listed as "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
MI
County
Shiawassee
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
—
Point of Interconnection
BELL ROAD - CORNELL 138.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-R5063