MISO-R5086
593 MW storage in Pointe Coupee, LA · In queue since October 2025
593 MW
Capacity
0
Components
7 months
In Queue
—
IA Status
Total Duration
7 months
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-R5086 is a proposed battery storage project with a total capacity of 593 MW, located in Pointe Coupee County, Louisiana. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue with an entry date of October 17, 2025. It is currently in active status within the queue and proposes to interconnect at the Big Cajun II 500kV Substation.
The project's service type is designated as NRIS (Network Resource Interconnection Service). The developer is unknown.
Generated from interconnection queue and public data sources
State
LA
County
Pointe Coupee
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
NRIS
Point of Interconnection
Big Cajun II 500kV Substation
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- LOUISIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.