Surplus; J893
10 MW hybrid in — · In queue since June 2020
10 MW
Capacity
1
Components
Other
5y 11m
In Queue
—
IA Status
Total Duration
5y 11m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed Surplus; J893 development project is a 10 MW hybrid energy project consisting of 10 MW of battery storage. It is located within the Midcontinent Independent System Operator (MISO) region. The project entered the MISO interconnection queue as queue ID S1000 on June 20, 2020.
The project is currently listed as active in the interconnection queue. Recent news coverage has discussed the project's progress within the MISO queue.
Generated from interconnection queue and public data sources
State
—
County
—
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
MISO
Service Type
—
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Surplus; J893