Surplus; J1000
25 MW hybrid in Grant, WI · In queue since May 2022 · Proposed COD March 2023
25 MW
Capacity
1
Components
Other
4 years
In Queue
—
IA Status
COD target: 2023
Total Duration
10 months
Schedule
38 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-03-27
The Surplus; J1000 development project is a proposed 25 MW hybrid energy project located in Grant County, Wisconsin. The project, consisting of a 25 MW battery component and an additional 25 MW component of unspecified "Other" technology, is in the Midcontinent Independent System Operator (MISO) interconnection queue as project S1023. The queue entry date is May 16, 2022, with a proposed commercial operation date of March 27, 2023.
The project is interconnected to the American Transmission Company via the Nelson Dewey - Lancaster 138kV point of interconnection. The project is currently listed as active in the MISO queue. Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
State
WI
County
Grant
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
AMERICAN TRANSMISSION COMPANY
Entity
MISO
Service Type
—
Point of Interconnection
Nelson Dewey - Lancaster 138kV
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WPS.LAKEFRN95
- POI Substation
- DEWEY
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Surplus; J1000