Surplus; J1369
50 MW hybrid in Dubois, IN · In queue since May 2022 · Proposed COD July 2022
50 MW
Capacity
1
Components
Other
4 years
In Queue
IA Executed
IA Status
Signed Oct 2022
Queue → IA
5 months
Total Duration
5 months
Schedule
47 months past proposed COD
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2022-07-01
The Surplus; J1369 development project is a proposed 50 MW hybrid battery storage project located in Dubois County, Indiana. Interconnecting to the Dubois - Culley 138kV line, the project is in the Midcontinent Independent System Operator (MISO) interconnection queue as entry S1026, with a queue entry date of May 26, 2022. The utility is Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South.
The proposed commercial operation date for the project was July 1, 2022. An Interconnection Agreement (IA) for the project has been executed as of October 31, 2022.
Generated from interconnection queue and public data sources
State
IN
County
Dubois
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
Southern Indiana Gas & Electric Company d/b/a Centerpoint Energy Indiana South
Entity
MISO
Service Type
—
Point of Interconnection
Dubois - Culley 138kV line
Data Source
LBNL + Live
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.