MISO-S1073
150 MW generation in Webster · In queue since February 2025
150 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-S1073 is a proposed 150 MW generation project located in Webster County, Kentucky. The project, listed under the utility BIG RIVERS ELECTRIC CORPORATION, entered the MISO interconnection queue on February 19, 2025. The point of interconnection is the Hopkins to Reid EVH 161kV line.
The project's interconnection service type is System Impact Study (SIS), and its status is currently listed as active within the MISO queue. The technology type is categorized as "Other".
Generated from interconnection queue and public data sources
State
—
County
Webster
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
BIG RIVERS ELECTRIC CORPORATION
Entity
MISO
Service Type
SIS
Point of Interconnection
Hopkins to Reid EVH 161kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.