MISO-S1074
200 MW generation in Phillips · In queue since February 2025
200 MW
Capacity
0
Components
1y 3m
In Queue
—
IA Status
Total Duration
1y 3m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-S1074 is a proposed 200 MW generation project located in Phillips County, Arkansas. The project, which utilizes an unspecified "Other" technology, is being developed by Entergy Arkansas, LLC. It is interconnected to the Ritchie Plant 230 kV Substation.
The project entered the MISO interconnection queue on February 28, 2025. It currently has an active status in the queue and is undergoing a System Impact Study (SIS). No proposed commercial operation date or interconnection agreement (IA) status is available.
Generated from interconnection queue and public data sources
State
—
County
Phillips
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
ENTERGY ARKANSAS, LLC
Entity
MISO
Service Type
SIS
Point of Interconnection
Ritchie Plant 230 kV Substation
Data Source
Live · MISO
- ISO / RTO
- MISO
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-S1074