Project MISO-S1080 — Project Summary

Queue ID
MISO-S1080
Capacity
150 MW
Technology
Battery
Status
active
Location
Martin, MN
Region
MISO
Developer
IA Status

MISO-S1080

MISO-S1080BetaActiveBattery StorageMISOLive · MISO

150 MW storage in Martin, MN · In queue since January 2025

150 MW

Capacity

0

Components

1y 4m

In Queue

IA Status

Interconnection

Total Duration

1y 4m

Pre-Study0%
Queue EntryJan 14, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

MISO-S1080 is a proposed 150 MW battery storage project located in Martin County, Minnesota. The project is sponsored by Southern Minnesota Municipal Power Agency. It is an active project in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on January 14, 2025. The designated point of interconnection (POI) is Rutland.

The project is undergoing a System Impact Study (SIS) as part of its interconnection service. There is no proposed commercial operation date available. The project has not appeared in recent news coverage and is not linked to an existing operating plant in the Energy Information Administration (EIA) database.

Generated from interconnection queue and public data sources

Project Details

State

MN

County

Martin

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

SOUTHERN MINNESOTA MUNICIPAL POWER AGENCY

Entity

MISO

Service Type

SIS

Point of Interconnection

Rutland

Data Source

Live · MISO

Market Context
Approximate
ISO / RTO
MISO
Trading Hub
MINN.HUB
Hub Confidence
HIGH
POI Substation
Rutland Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project MISO-S1080