MISO-S1081
100 MW storage in Muskegon, MI · In queue since January 2025
100 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
Total Duration
1y 4m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-S1081 is a proposed 100 MW battery storage project located in Muskegon County, Michigan. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, with an entry date of January 13, 2025. The designated point of interconnection (POI) is the DU PONT - WHITE LAKE 138.0kV substation.
The project's service type is System Impact Study (SIS). The interconnecting utility is METC. As of the latest data, the project remains in active status within the MISO queue.
Generated from interconnection queue and public data sources
State
MI
County
Muskegon
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
METC
Entity
MISO
Service Type
SIS
Point of Interconnection
DU PONT - WHITE LAKE 138.0kV
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MICHIGAN.HUB
- Hub Confidence
- HIGH
- POI Substation
- White Lake
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-S1081