MISO-S1083
100 MW storage in Hancock, KY · In queue since January 2025
100 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
Total Duration
1y 4m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-S1083 is a proposed 100 MW battery storage project located in Hancock County, Kentucky. The project is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered the queue on January 14, 2025. Big Rivers Electric Corporation is the utility associated with the project.
The project's service type is System Impact Study (SIS), and its status is currently listed as active within the MISO queue.
Generated from interconnection queue and public data sources
State
KY
County
Hancock
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
BIG RIVERS ELECTRIC CORPORATION
Entity
MISO
Service Type
SIS
Point of Interconnection
Skillman
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-S1083