MISO-S1084
150 MW storage in Greene, IN · In queue since January 2025
150 MW
Capacity
0
Components
1y 4m
In Queue
—
IA Status
Total Duration
1y 4m
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-S1084 is a proposed 150 MW battery storage project located in Greene County, Indiana. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, having entered on January 13, 2025. Hoosier Energy is the utility associated with the project.
The project's interconnection service type is System Impact Study (SIS), and its queue status is currently active. The point of interconnection (POI) is Worthington.
Generated from interconnection queue and public data sources
State
IN
County
Greene
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
HOOSIER ENERGY
Entity
MISO
Service Type
SIS
Point of Interconnection
Worthington
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- HIGH
- POI Substation
- Worthington Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.