Project MISO-S1086 — Project Summary

Queue ID
MISO-S1086
Capacity
Technology
Other
Status
active
Location
Stoddard
Region
MISO
Developer
IA Status

MISO-S1086

MISO-S1086BetaActiveMISOLive · MISO

generation in Stoddard · In queue since February 2025

Capacity

0

Components

1y 3m

In Queue

IA Status

Interconnection

Total Duration

1y 3m

Pre-Study0%
Queue EntryFeb 18, 2025

Interconnection request submitted to ISO/RTO

DPP Study

MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.

Typical: 30–40 months (historical); 12 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

MISO-S1086 is a proposed generation project of unspecified technology located in Stoddard County, Missouri. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue, with a queue entry date of February 18, 2025. Ameren Missouri is the interconnecting utility.

The project's interconnection service type is System Impact Study (SIS). The project's status is currently listed as active.

Generated from interconnection queue and public data sources

Project Details

State

County

Stoddard

Grid Region

MISO (Midcontinent)

Market

ISO/RTO Member

Developer

Utility

AMEREN MISSOURI

Entity

MISO

Service Type

SIS

Point of Interconnection

Stoddard - Morley 161kV

Data Source

Live · MISO

Market Context
Approximate
ISO / RTO
MISO
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.