MISO-S1110
100 MW storage in Chisago, MN · In queue since August 2025
100 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
Total Duration
9 months
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
MISO-S1110 is a proposed 100 MW battery storage project located in Chisago County, Minnesota. The project is in the Midcontinent Independent System Operator (MISO) interconnection queue as of August 22, 2025. Northern States Power Company is the interconnecting utility.
The project is listed as active in the queue for a System Impact Study (SIS). No proposed commercial operation date or Interconnection Agreement (IA) status is available. The point of interconnection (POI) is at Chisago County.
Generated from interconnection queue and public data sources
State
MN
County
Chisago
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
NORTHERN STATES POWER COMPANY
Entity
MISO
Service Type
SIS
Point of Interconnection
CHISAGO COUNTY
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project MISO-S1110