MISO-S1111
263 MW generation in Adair, IA · In queue since July 2025
263 MW
Capacity
0
Components
10 months
In Queue
—
IA Status
Total Duration
10 months
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed MISO-S1111 project is a 263 MW hybrid generation project located in Adair County, Iowa. The project, which is listed in the Midcontinent Independent System Operator (MISO) interconnection queue, is being developed by MidAmerican Energy Co. It entered the queue on July 31, 2025.
The project's interconnection status is active, and it is undergoing a System Impact Study (SIS). The technology is listed as "Other" with a detail of "Hybrid", but further component details are not available.
Generated from interconnection queue and public data sources
State
IA
County
Adair
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
MIDAMERICAN ENERGY CO.
Entity
MISO
Service Type
SIS
Point of Interconnection
ORIENT
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- MINN.HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MEC.ORIENT1
- POI Substation
- Orient Wind Farm