MISO-S1112
130 MW storage in Pike, IN · In queue since August 2025
130 MW
Capacity
0
Components
9 months
In Queue
—
IA Status
Total Duration
9 months
Interconnection request submitted to ISO/RTO
MISO uses the Definitive Planning Phase (DPP) process with 3 study phases.
Typical: 30–40 months (historical); 12 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed MISO-S1112 project is a 130 MW battery storage development in Pike County, Indiana. The project is located within the Midcontinent Independent System Operator (MISO) region and is being proposed by Southern Indiana Gas & Electric Company d/b/a CenterPoint Energy Indiana South.
The project entered the MISO interconnection queue on August 11, 2025. The point of interconnection is the Cato 138/69kV substation. The project's service type is System Impact Study (SIS) and its interconnection status is active.
Generated from interconnection queue and public data sources
State
IN
County
Pike
Grid Region
MISO (Midcontinent)
Market
ISO/RTO Member
Developer
—
Utility
SOUTHERN INDIANA GAS & ELECTRIC COMPANY D/B/A CENTERPOINT ENERGY INDIANA SOUTH
Entity
MISO
Service Type
SIS
Point of Interconnection
Cato 138/69kV (facilities above 100kV)
Data Source
Live · MISO
- ISO / RTO
- MISO
- Trading Hub
- INDIANA.HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.